Snapshot

22 civic action(s) on community_hub across 8 meeting(s) (2024-01-15 to 2024-12-09).

Timeline

2024-01-15 — Combined Council Meeting - January 15 2024 (Minutes)

Chatham-Kent Community Hub (vote; carried (10-5))

The contract amendment in the amount of $166,098.97 (including HST) for Project Management and Development Services of the Chatham-Kent Community Hub, be approved to Nustadia Recreation Inc. and funded from the Building Lifecycle Reserve.

Source: Combined Council Meeting - January 15 2024 (Minutes) — Item 18(a)

2024-02-26 — Combined Council Meeting - February 26 2024 (Minutes)

Community Hub Stakeholder Engagement - Architectural Conservancy of Ontario representative (vote; defeated (7-7))

2. Local representative from Architectural Conservancy of Ontario"

Source: Combined Council Meeting - February 26 2024 (Minutes) — Item 17(b)

Community Hub Stakeholder Engagement - Art Advisory Committee representative (vote; carried (12-2))

3. Art Advisory Committee”

Source: Combined Council Meeting - February 26 2024 (Minutes) — Item 17(b)

Community Hub Stakeholder Engagement - Municipal Heritage Committee representative (vote; defeated (6-8))

Municipal Heritage Committee

Source: Combined Council Meeting - February 26 2024 (Minutes) — Item 17(b)

2024-09-23 — Combined Council Meeting - September 23 2024 (Minutes)

Deputations regarding the former Sears building proposal (notice_of_motion; —)

Councillor Storey presented a notice of motion regarding Deputations regarding the former Sears building proposal.

Source: Combined Council Meeting - September 23 2024 (Minutes) — Item 18

2024-10-07 — Council Meeting - October 7 2024 (Minutes)

Deputations regarding the former Sears building proposal (vote; carried (15-1))

In-person deputations are permitted for the October 21st Council meeting (open session) regarding the next phase of this proposal.

Source: Council Meeting - October 7 2024 (Minutes) — Item 16(b)

Access for all residents to the proposed Chatham-Kent Community Hub (notice_of_motion; —)

Councillor Storey presented a notice of motion regarding ensuring access for all residents to the proposed Chatham-Kent Community Hub.

Source: Council Meeting - October 7 2024 (Minutes) — Item 21

Chatham-Kent Community Hub (notice_of_motion; —)

Councillor Jubenville presented a notice of motion regarding the Chatham-Kent Community Hub.

Source: Council Meeting - October 7 2024 (Minutes) — Item 21

Referendum on the Chatham-Kent Community Hub (notice_of_motion; —)

Councillor Jubenville presented a notice of motion regarding Referendum on the Chatham-Kent Community Hub.

Source: Council Meeting - October 7 2024 (Minutes) — Item 21

2024-10-21 — Combined Council Meeting - October 21 2024 (Minutes)

Chatham-Kent Community Hub - Comparative Cost Estimates Direction (vote; carried (14-2))

That Administration be directed to provide updated high level cost estimates for upgrading the Civic Centre, museum and the Library (including the expansion to 35,000 sq. ft) to the same standards being proposed for the Chatham-Kent Community Hub

Source: Combined Council Meeting - October 21 2024 (Minutes) — Item 16(a)

Chatham-Kent Community Hub - Detailed Design Authorization (vote; carried (11-5))

The completion of the detailed design for the Chatham-Kent Community Hub project inclusive of the Park Avenue Business Centre alterations be awarded to Architecturra Inc. in the amount of $2,177,683.46 (including HST), funded from the Buildings Lifecycle Reserve.

Source: Combined Council Meeting - October 21 2024 (Minutes) — Item 16(a)

Chatham-Kent Community Hub - Fixed Cost RFP Direction (vote; carried (14-3))

Upon the completion of the detailed design for the Chatham-Kent Community Hub, that a fixed cost request for proposal be implemented to ensure the cost associated with project assures the community that over runs won't occur and that detailed project cost will be determined prior to moving the project forward.

Source: Combined Council Meeting - October 21 2024 (Minutes) — Item 16(a)

Motion by Councillor Storey re Ensuring access to the Downtown Chatham Hub (Postponed) (agenda_item; deferred)

This motion was postponed to the November 18, 2024 Council Meeting.

Source: Combined Council Meeting - October 21 2024 (Minutes) — Item 16(h)

Motion by Councillor Jubenville re CK Community Hub (Ruled out of order) (agenda_item; unknown)

Therefore, the motion of Councillor Jubenville’s relating to the Sears Building is a Motion to Reconsider.

Source: Combined Council Meeting - October 21 2024 (Minutes) — Item 16(i)

Motion by Councillor Jubenville re Referendum on CK Community Hub (Postponed) (agenda_item; deferred)

This motion was postponed to the November 4, 2024 Council Meeting.

Source: Combined Council Meeting - October 21 2024 (Minutes) — Item 17(c)

2024-11-04 — Council Meeting - November 4 2024 (Minutes)

Referendum re Chatham-Kent Community Hub (vote; defeated (6-11))

“That Council direct Administration to complete a report pursuant to the Municipal Elections Act complete with how to proceed in the most efficient and fiscally responsible way with a Referendum in Chatham-Kent.”

Source: Council Meeting - November 4 2024 (Minutes) — Item 17(e)

2024-11-18 — Combined Council Meeting - November 18 2024 (Minutes)

Motion by Councillor Storey re Ensuring access for all residents to the Chatham-Kent Community Hub (Postponed) (motion; deferred)

This item was postponed to the December 9, 2024 Council Meeting.

Source: Combined Council Meeting - November 18 2024 (Minutes) — Item 20(d)

2024-12-09 — Council Meeting - December 9 2024 (Minutes)

CK Community Hub Accessibility Standards (Recommendations 1 & 2) (vote; carried (17-1))

That Chatham-Kent staff provide a summary of the accessibility standards that the CK Hub detailed design will reference and leverage to meet best practices for current accessibility design,

Source: Council Meeting - December 9 2024 (Minutes) — Item 16(c)

CK Community Hub Costing Standards Exceeding Requirements (Recommendation 5) (vote; defeated (9-9))

Recommendations from the AAC and stakeholder groups that exceed current standards are costed out and included in upcoming Council reports on this proposal.

Source: Council Meeting - December 9 2024 (Minutes) — Item 16(c)

CK Community Hub Parking Accessibility Review (Recommendation 4) (vote; carried (11-7))

A list of parking distance and parking accessibility features of the proposed site are reviewed with the ACC and included in the next Report to Council on this item.

Source: Council Meeting - December 9 2024 (Minutes) — Item 16(c)

CK Community Hub Traffic/Pedestrian Studies (Recommendation 3) (vote; defeated (5-13))

This planning will include standard studies for a project of this type and size, which includes passenger and pedestrian load, modelling and traffic flows in and around the entire property,

Source: Council Meeting - December 9 2024 (Minutes) — Item 16(c)

CK Community Hub Universal Design Assessment (Recommendation 6) (vote; defeated (5-13))

An assessment of universal design experience of the current team is done and reviewed with AAC;

Source: Council Meeting - December 9 2024 (Minutes) — Item 16(c)