Issue Timeline: bridge
Full evidence timeline (the richer view). For a compact one-line list, see the issue summary.
Snapshot
3 civic action(s) on bridge across 3 meeting(s) (2024-08-12 to 2026-06-22).
- Meetings involved: 3
- 2024-08-12 — Combined Council Meeting - August 12 2024 (Minutes)- 2026-05-11 — Council Meeting - May 11 2026 (Minutes)- 2026-06-22 — Combined Council Meeting - June 22 2026 (Minutes)
- Councillors involved: C. McGregor, Finn, Hall
- Split votes: 0
- Budget-related actions: 1
- Needs review: 1
Timeline
2024-08-12 — Combined Council Meeting - August 12 2024 (Minutes)
Contract Amendment - LO Stonehouse Memorial Walk Bridge Rehabilitation (T23-217) (vote; carried (17-0))
- Mover: C. McGregor, Seconder: Hall
- Summary: Council approved contract amendments for the LO Stonehouse Memorial Walk Bridge Rehabilitation totalling $581,950 to Dayson Industrial Services Inc. and Dillon Consulting Limited, funded by a transfer of $524,064.00 from the Lifeamp Bridge Reserve. Moved by Councillor C. McGregor, seconded by Councillor Hall.
- Related tags: infrastructure, procurement
- Entities: Dayson Industrial Services Inc., Dillon Consulting Limited
A contract amendment in the amount of $480,250.00 (including HST) for the LO Stonehouse Memorial Walk Bridge Rehabilitation be approved for Dayson Industrial Services Inc.
Source: Combined Council Meeting - August 12 2024 (Minutes) — Item 16(b)
2026-05-11 — Council Meeting - May 11 2026 (Minutes)
Talbot Trail and 2nd Concession Bridge update (question; unknown)
- Named councillor: Councillor Finn
- Summary: Councillor Finn requested an update, and the Director of Engineering Services responded.
- Related tags: roads, infrastructure
- Entities: Talbot Trail, 2nd Concession Bridge, Director of Engineering Services, Ministry
Councillor Finn requested an update on Talbot Trail and the condition of the 2nd Concession Bridge. The Director of Engineering Services explained that all of the archeological field work has been completed. Currently working through the review and approval with the Ministry on the reporting piece. The engineering is complete and the tender is being written. Staff are working with utility companies about their relocation along the new road alignment. The 2nd Concession Bridge was inspected and some repairs have been identified that will form part of the realignment project.
Source: Council Meeting - May 11 2026 (Minutes) — Item 26
2026-06-22 — Combined Council Meeting - June 22 2026 (Minutes)
Dufferin Avenue Bridge rehabilitation (vote; carried)
- Mover: —
- Summary: The Dufferin Avenue Bridge rehabilitation report was approved through the consent agenda.
- Related tags: procurement, infrastructure
- Entities: Dufferin Avenue, Running Creek, KB Civil Constructors Inc., GEI Consultants Canada Ltd.
- Needs human review: Vote result not fully recorded, Evidence excerpt is long or vague
c.Tender Award – Contract T26-189 – Dufferin Avenue Bridge Rehabilitation over Running Creek
"That
The tender in the amount of $1,949,148.83 (excluding HST) for the Dufferin Avenue Bridge Rehabilitation over Running Creek be awarded to KB Civil Constructors Inc.
A Contract Amendment in the amount of $74,200.00 (excluding HST) for Contract Administration and Inspection Services, be approved for GEI Consultants Canada Ltd.
The project be partially funded by a transfer of $183,959.77 from the Lifeamp Bridge Lifecycle Reserve to the Dufferin Avenue Bridge over Running Creek project account (18ENG2061).
The Mayor and Clerk be authorized to enter into the recommended agreements."
This report was approved as part of the Consent Agenda.
Source: Combined Council Meeting - June 22 2026 (Minutes) — Item 17(c)